Parisi Law Firm — Personal Injury & Business Lawyer in Jefferson, GA

Business Law · Resource Guide

Georgia Construction Payment Guide: Every Notice, Deadline, and Checklist

A job-by-job walkthrough for contractors, subcontractors, and suppliers: what to do before you start, in the first 30 days, at every pay application, when payment is late, and after you file.

The Short Answer

Getting paid on a Georgia construction job depends on hitting notices and deadlines in order: a Notice to Contractor within 30 days when a Notice of Commencement is filed, a claim of lien within 90 days, and suit within 365 days. Deadlines are strict. This guide is general information, not legal advice for your specific job.

Most contractors don't lose lien or bond rights because the money wasn't owed. They lose them because a notice went out late, a waiver was signed too early, or a lawsuit was filed without the follow-up paperwork. Georgia's construction payment rules are spread across several statutes, and each one has its own clock. This guide puts them in the order you'll actually meet them on a job, with printable checklists and a link to a detailed page for each step.

Use it as a map, not a substitute for advice. Every project is different: who owns the property, what was filed at the courthouse, what your contract says, and where you sit in the payment chain all change the answer. If a deadline is close or something doesn't fit, call Parisi Law Firm at (404) 594-5130. Jerry Parisi works directly with trade businesses in Jefferson, Jackson County, Northeast Georgia, and metro Atlanta.

Before the job starts

Most payment problems are cheaper to prevent than to fix. Do this before you mobilize or ship the first load. Our construction contracts page covers contract review in detail.

  • Review the contract: payment terms, retainage, change-order procedure, pay-if-paid or pay-when-paid language, dispute resolution, and any lien waiver clause. Georgia enforces a pay-if-paid clause when the condition is clearly expressed.
  • Know that a waiver of lien or payment-bond rights signed before you furnish labor or materials is void under O.C.G.A. § 44-14-366(b), even if it is buried in the contract.
  • Suppliers: get a signed credit application with a personal guaranty where you can, and record the project name, address, and owner for every account.
  • Check the county superior court clerk's records for a Notice of Commencement. If one is filed, note the owner, contractor, surety, and lender it lists.
  • Identify the owner: private, State of Georgia, a county, city, or school board, or the federal government. Public property can't be liened, so the remedy on public jobs is a payment bond claim.
  • On public jobs, request a copy of the payment bond and note the surety. On federal jobs, the contracting officer must provide the surety's name and a copy of the bond on request.
  • Set up a job file: contract, change orders, delivery tickets, daily logs, invoices, and a calendar for every deadline in this guide.

In the first 30 days

The first month sets up your notice rights. See our Notice of Commencement and Notice to Contractor pages for the details and required contents.

  • Notice of Commencement (private jobs): the owner, the owner's agent, or the contractor files it with the superior court clerk no later than 15 days after the contractor physically starts work, and posts a copy on the site (O.C.G.A. § 44-14-361.5).
  • Notice to Contractor: if a Notice of Commencement is filed and you have no contract with the prime contractor, send it within 30 days of the NOC filing or 30 days after your first delivery, whichever is later, by registered or certified mail or statutory overnight delivery to the owner and the contractor at the addresses on the NOC. Missing a required notice defeats your lien.
  • No Notice of Commencement on file? The Notice to Contractor requirement doesn't apply. Keep checking the clerk's records, because a late NOC can still trigger it.
  • Preliminary notice of lien rights (O.C.G.A. § 44-14-361.3) is optional. You may file one within 30 days after you first deliver labor or materials, but you can enforce a lien without it.
  • Public projects: the prime contractor posts and files a Notice of Commencement within 15 days of starting work. If one is filed, a claimant with no contract with the prime gives the contractor written notice within 30 days of the filing or first delivery, whichever is later (O.C.G.A. §§ 13-10-63, 36-91-93).
  • Federal projects: calendar the Miller Act 90-day notice from your last day of work if you are a second-tier sub or supplier.

Every pay application

Payment timing and lien waivers are where money quietly slips away. Our Prompt Payment Act and lien waivers pages go deeper.

  • Prompt Pay timing: the owner pays the contractor within 15 days of receiving a payment request, and the contractor pays each sub within 10 days of actually receiving payment for that sub's work (O.C.G.A. § 13-11-4). Contracts can set different terms.
  • Late-payment interest is 1% per month, but only if the party you're billing was notified of O.C.G.A. § 13-11-7 when you requested payment. Put that notice on every pay app. Accepting the payment releases the interest claim.
  • The Prompt Pay Act doesn't apply to residential projects of 12 or fewer units.
  • Lien waivers: use only the statutory Interim or Final 'Waiver and Release of Lien and Payment Bond Rights' form, and sign it only for money you have actually received.
  • Calendar 90 days from the date you sign every waiver. The waiver becomes effective at the end of that period even if you were never paid, unless you file an affidavit of nonpayment first.
  • Not paid? File the affidavit of nonpayment in the county where the property sits before the 90 days run, and send a copy to the owner within 7 days. Filing a lien does not stop a waiver; only the affidavit does.
  • A statutory waiver releases only lien and bond rights. Your contract claim for the money survives.

When payment is late

Once payment slips, the clocks keep running whether or not the customer is still promising a check. Verbal promises to pay do not extend a lien deadline.

  • Send a written demand that states the amount owed, the work it covers, and the deadline to pay.
  • Private jobs: record a claim of lien with the superior court clerk in the county where the property is located within 90 days after you complete your work or furnish materials (O.C.G.A. § 44-14-361.1). Weekends and holidays do not extend that deadline.
  • The lien must include the 395-day expiration statement in at least 12-point bold type and a notice of the owner's right to contest, or it is invalid.
  • No later than 2 business days after filing, send a copy of the lien to the owner by registered or certified mail or statutory overnight delivery. If a Notice of Commencement was filed, also send a copy to the contractor at the address on the NOC.
  • Georgia public jobs: if no Notice of Commencement was filed, a claimant with no contract with the prime gives written notice to the contractor within 90 days after its last labor or materials. See our public project bond claims page.
  • Federal jobs: second-tier subs and suppliers give written notice to the prime within 90 days of their last labor or materials (40 U.S.C. § 3133). First-tier claimants may sue once they are unpaid 90 days after their last work. See our Miller Act page.
  • Suppliers chasing open accounts: see our material supplier collections page for demand, guaranty, and lien options.

After you file

Filing the lien is not the finish line. Two more filings keep it alive, and the owner has tools to speed up the clock.

  • Start a lawsuit (or arbitration, if your contract requires it) to enforce the lien within 365 days of filing the lien.
  • Within 30 days after starting that action, file a sworn notice of commencement of lien action with the clerk in the county where the lien was recorded. Missing either step makes the lien unenforceable (O.C.G.A. § 44-14-367).
  • If the owner or contractor records a Notice of Contest of Lien, your time to start a lien action shrinks to 60 days from receipt of that notice (O.C.G.A. § 44-14-368).
  • The owner or contractor can discharge the lien from the property by posting a bond for double the amount claimed, or the amount claimed if the property is the owner's home (O.C.G.A. § 44-14-364). You then pursue the bond, but you still must meet the suit deadlines.
  • Georgia public bond suits must be filed within one year after the contract is completed and the work is accepted (O.C.G.A. §§ 13-10-65, 36-91-95).
  • Miller Act suits go in federal district court where the contract was performed, within one year after your last labor or materials.
  • Consider mediation or arbitration if your contract calls for it. Our construction mediation and arbitration page explains how that fits with lien deadlines.

Checklist for owners and general contractors

The same rules protect owners and GCs who use them. A few habits cut down on surprise liens and double payment.

  • File a complete Notice of Commencement within 15 days of starting work, with the legal description, true owner, surety, and lender. A defective NOC can make the Notice to Contractor rule inapplicable.
  • Post the NOC on site and give a copy to any sub or supplier who asks in writing within 10 calendar days.
  • Collect the statutory Interim or Final waiver form from every sub and supplier with each payment, and track affidavits of nonpayment filed in the county.
  • Pay subs within the Prompt Pay window, and document any withholding for a reason the Act allows, such as defective work that hasn't been fixed or disputed work.
  • Lien on your property? Check whether it was filed within 90 days, whether the copy was sent within 2 business days, and whether it carries the required 395-day statement. Then consider a Notice of Contest or a discharge bond.

Georgia construction payment deadlines at a glance

StepDeadlineWhoLaw
Notice of Commencement (private)No later than 15 days after the contractor physically starts workOwner, owner's agent, or contractorO.C.G.A. § 44-14-361.5
Notice to Contractor (private)30 days from NOC filing or first delivery, whichever is later (only if an NOC is filed)Subs and suppliers with no contract with the primeO.C.G.A. § 44-14-361.5
Owner pays contractorWithin 15 days of receiving a payment requestOwnerO.C.G.A. § 13-11-4
Contractor pays subWithin 10 days of receiving paymentContractor and each subO.C.G.A. § 13-11-4
Affidavit of nonpaymentBefore 90 days after signing the lien waiverAnyone who signed a waiver and wasn't paidO.C.G.A. § 44-14-366
Claim of lienWithin 90 days after completing work or furnishing materialsContractors, subs, suppliers, and others with lien rightsO.C.G.A. § 44-14-361.1
Copy of lien to ownerNo later than 2 business days after filingLien claimantO.C.G.A. § 44-14-361.1
Lien enforcement suitWithin 365 days of filing the lienLien claimantO.C.G.A. § 44-14-361.1
Notice of commencement of lien actionWithin 30 days after starting the suitLien claimantO.C.G.A. § 44-14-361.1
Suit after a Notice of Contest60 days from receipt of the noticeLien claimantO.C.G.A. § 44-14-368
Public bond notice (NOC filed)30 days from NOC filing or first delivery, whichever is laterClaimants with no contract with the primeO.C.G.A. §§ 13-10-63, 36-91-93
Public bond notice (no NOC)Within 90 days after last labor or materialsClaimants with no contract with the primeO.C.G.A. §§ 13-10-63, 36-91-93
State or local public bond suitWithin 1 year after completion and acceptance of the workBond claimantO.C.G.A. §§ 13-10-65, 36-91-95
Public retainage releaseOwner pays within 30 days after substantial completion and invoice; passed down within 10 daysPublic owner, contractor, subsO.C.G.A. § 13-10-80
Miller Act noticeWithin 90 days after last labor or materialsSecond-tier subs and suppliers40 U.S.C. § 3133
Miller Act suitWithin 1 year after last labor or materialsFirst- and second-tier claimants40 U.S.C. § 3133

Frequently Asked Questions

What is the most important deadline for a Georgia contractor who isn't paid?

On a private job, the 90-day claim of lien deadline, measured from when you complete your work or furnish materials. Weekends and holidays don't extend it. But earlier deadlines can matter just as much: if a Notice of Commencement was filed and you needed to send a Notice to Contractor within 30 days, missing that notice defeats the lien.

Do I need to send a notice before I can file a lien in Georgia?

It depends on what was filed. If a Notice of Commencement is on file and you have no contract with the prime contractor, Georgia requires a Notice to Contractor within 30 days of the NOC filing or your first delivery, whichever is later. The separate preliminary notice of lien rights is optional.

Can I file a lien on a public school or county project?

No. Public property can't be liened in Georgia. Your remedy on state and local public work is a claim against the contractor's payment bond, which has its own notice rules and a one-year suit deadline from completion and acceptance. Federal projects follow the Miller Act instead.

What happens if I sign a lien waiver and the check never clears?

A Georgia statutory waiver becomes effective 90 days after you sign it, even if you were never paid, unless you file an affidavit of nonpayment in the county before that period ends. Filing a lien doesn't stop the waiver. Your contract claim for the money survives either way.

Is filing the lien enough to protect my claim?

No. You must start an action to enforce the lien within 365 days of filing it, and file a notice of commencement of lien action within 30 days after starting that action. Missing either makes the lien unenforceable. If the owner records a Notice of Contest, your time to sue drops to 60 days from receipt.

Does the Georgia Prompt Pay Act apply to my job?

It covers most commercial work and many public owners, and suppliers count as subcontractors. It does not apply to residential projects of 12 or fewer units, or to counties under 10,000 people and cities under 2,500. Parties can also agree by contract to different payment terms.

How can an owner get a lien off the property quickly?

The owner or contractor can post a bond with the superior court clerk for double the amount claimed, or the amount claimed if the property is the owner's home. Once approved, the property is discharged from the lien and the claimant must pursue the bond, still meeting the suit deadlines.

Is this guide legal advice for my project?

No. It is general information about Georgia and federal construction payment rules. Your rights depend on your contract, your place in the payment chain, the owner, and what was filed at the courthouse. For advice on a specific job, schedule a consultation with Parisi Law Firm at (404) 594-5130.

Protect Your Business

Whether you need a contract reviewed, a lien filed, or a dispute resolved, Parisi Law Firm is ready to help Georgia business owners get it done right.

(404) 594-5130

Free. Confidential. No Obligation.

Ready to Talk?
We're Here to Help.

Get a 100% free case review from Jerry Parisi. You don't pay a single dollar unless we win your case.

Call NowFree Consultation