Mechanic's Liens
Georgia Mechanic's Lien Deadlines: Don't Lose Your Right to Payment
Reviewed by Jerry Parisi, Attorney · State Bar of Georgia No. 881415, admitted 2015 · Last reviewed . Verify with the State Bar.
- In Georgia you must file a claim of lien within 90 days after you finish your work or furnish your materials, in the superior court clerk's office of the county where the property is located (O.C.G.A. § 44-14-361.1(a)(2)).
- No later than 2 business days after filing, send a copy of the lien to the property owner by registered or certified mail or statutory overnight delivery.
- A filed lien only preserves your claim. You must start a lien action within 365 days of filing the lien, and file a notice of commencement of lien action within 30 days after starting it.
- If the owner or contractor records a Notice of Contest of Lien, your time to start the lien action shrinks to 60 days from receiving it.
- If a Notice of Commencement was filed and you have no contract with the general contractor, you must send a Notice to Contractor within 30 days or you lose the lien.
- Signed a lien waiver but weren't paid? Since January 1, 2021 you have 90 days to file an affidavit of nonpayment.
A mechanic's lien is one of the most powerful tools a Georgia contractor, subcontractor or supplier has for getting paid, but it only works if every deadline is met in the right order. Georgia's lien statute says it plainly: on failure of any of the required steps, "the lien shall not be effective or enforceable" (O.C.G.A. § 44-14-361.1(a)). File a day late, mail the owner's copy a day late, or let the lawsuit window close, and the lien you were counting on can disappear.
This guide walks through each deadline in order, with the statute behind it, a timeline table you can work from, a worked example with real calendar dates, and what changed in 2021. If you are close to a deadline now, talk to a business law attorney before the date passes, not after.
Why Georgia lien deadlines are so unforgiving
Georgia's lien statutes balance two interests: giving contractors, subcontractors and suppliers a real way to force payment, and protecting owners from claims that linger on their title. The legislature struck that balance with fixed deadlines and required content rather than case-by-case fairness calls, and the statute itself says a lien that misses a required step is not effective or enforceable.
The practical lesson is simple: track your dates from the day you start a job, not after a payment dispute starts. And file early. Do not plan on a weekend or holiday pushing a lien deadline to the next business day.
Georgia mechanic's lien timeline at a glance
Here is every deadline in the order it usually comes up. Not every step applies to every job: the Notice to Contractor applies only when a Notice of Commencement was filed and you have no contract with the general contractor, and the Notice of Contest is something the other side files.
| Step | Deadline | Who | Statute |
|---|---|---|---|
| Notice of Commencement | Within 15 days after the contractor physically starts work | Owner, owner's agent or contractor | O.C.G.A. § 44-14-361.5(b) |
| Preliminary notice of lien rights (optional) | Within 30 days after first furnishing labor, services or materials; copy to the contractor or owner within 7 days | Potential lien claimant | O.C.G.A. § 44-14-361.3 |
| Notice to Contractor | Within 30 days after the Notice of Commencement is filed or your first delivery, whichever is later | Claimants with no contract with the general contractor | O.C.G.A. § 44-14-361.5(a) |
| File the claim of lien | Within 90 days after completing the work or furnishing the materials | Lien claimant | O.C.G.A. § 44-14-361.1(a)(2) |
| Send the owner a copy | No later than 2 business days after filing | Lien claimant | O.C.G.A. § 44-14-361.1(a)(2) |
| Start the lien action | Within 365 days after filing the lien | Lien claimant | O.C.G.A. §§ 44-14-361.1(a)(3), 44-14-367 |
| File notice of commencement of lien action | Within 30 days after starting the lien action | Lien claimant | O.C.G.A. § 44-14-361.1(a)(3) |
| Lien expires on its face | 395 days after filing if no notice of commencement of lien action is filed | Automatic | O.C.G.A. § 44-14-367 |
| After a Notice of Contest of Lien | Start the lien action within 60 days of receiving it; the lien is extinguished 90 days after the contest is filed if no notice of commencement of lien action is filed | Owner or contractor files; claimant responds | O.C.G.A. § 44-14-368 |
| Waiver signed, payment not received | Affidavit of nonpayment within 90 days of the waiver | Lien claimant | O.C.G.A. § 44-14-366 |
How long does a contractor have to file a lien in Georgia? 90 days
The claim of lien must be filed for record within 90 days after the completion of the work, or within 90 days after the material or machinery is furnished, in the office of the clerk of the superior court of the county where the property is located (§ 44-14-361.1(a)(2)). Not the county where your business is, and not where the contract was signed.
The lien states the date the claim became due, which the statute defines as "the last date the labor, services, or materials were supplied to the premises." That is a fact about work on the ground, not your invoice date, your payment terms, or the day the customer stopped answering. Keep dated records that prove it: delivery tickets, daily logs, timesheets and material receipts.
The form matters as much as the date. The lien has to include a statement about when it expires and a notice to the owner that the owner has the right to contest it; the absence of either invalidates the lien. The expiration statement must appear in at least 12-point bold type: "This claim of lien expires and is void 395 days from the date of filing of the claim of lien if no notice of commencement of lien action is filed in that time period" (§ 44-14-367). For the step-by-step filing process, see how to file a mechanic's lien in Georgia.
The 2-business-day copy to the owner
Filing with the clerk is the middle of the process, not the end. No later than two business days after the claim of lien is filed, you must send a true and accurate copy by registered or certified mail or statutory overnight delivery to the property owner. If the owner's address cannot be found, it goes to the contractor as the owner's agent. If the owner is an entity on file with the Georgia Secretary of State's Corporations Division, sending it to the entity's address or its registered agent's address satisfies the requirement.
If a Notice of Commencement was filed for the project, you must also send a copy to the contractor at the address shown on that notice. Build both mailings into your filing checklist so they go out the same day the lien is recorded.
The 365-day lien action and the 30-day notice that follows
A recorded lien secures your claim against the property, but it does not collect money by itself. If you are still unpaid, you must commence a lien action for the amount of your claim within 365 days from the date the lien was filed (§ 44-14-361.1(a)(3)). Missing that date makes the lien unenforceable (§ 44-14-367). Don't let settlement talks quietly run out the clock.
Then, within 30 days after commencing the lien action, file a notice with the clerk of the superior court of the county where the lien was filed. The notice identifies the court, the case style and number, the date the action was filed, and the book and page where the lien is recorded, and it must be executed under oath, though a missing oath is an amendable defect. A separate lis pendens is not needed. If no notice of commencement of lien action is filed within 395 days of the lien, the lien can be disregarded.
In some situations you do not have to sue the contractor first. If the contractor or subcontractor who hired you absconds, dies, leaves the state, or goes bankrupt, or if your contract includes a clause that prevents payment to you until the contractor is paid, you can enforce the lien directly against the property in a lien action against the owner, with the judgment limited to the property itself (§ 44-14-361.1(a)(4)). The owner can defend by proving payments were properly applied. Our guide to pay-if-paid vs. pay-when-paid clauses explains those clauses.
Counting the days on your own project? Request a consultation before a deadline passes.
Notice of Contest of Lien: when 365 days becomes 60
An owner or contractor (or their agent or attorney) can shorten your time to sue by recording a Notice of Contest of Lien and delivering it to you (§ 44-14-368). Once you receive it, you have 60 days to commence the lien action, and you still have to file the notice of commencement of lien action within 30 days after you file suit. The contesting party must mail you a copy within seven days of filing it, and service is complete on mailing.
If no notice of commencement of lien action is filed within 90 days after the Notice of Contest is filed, the lien is extinguished by law. When a contest arrives, treat it as the new controlling deadline and calendar it the day it comes in.
Early notices: Notice of Commencement, Notice to Contractor and preliminary notice
Some of Georgia's lien paperwork happens before any payment dispute. Some of it is optional and some of it is mandatory, and mixing them up can cost you the lien.
- Notice of Commencement: the owner, the owner's agent or the contractor files it with the superior court clerk within 15 days after the contractor physically commences work, and a copy is posted on the site. The contractor must give a copy to any subcontractor or supplier who asks in writing. If the contractor doesn't provide it within 10 calendar days of the request, the Notice to Contractor requirement does not apply to the person who asked.
- Notice to Contractor: mandatory when a Notice of Commencement was filed and you do not have a contract with the general contractor. Send it to the owner and the contractor, at the addresses in the Notice of Commencement, by registered or certified mail or statutory overnight delivery, within 30 days of the NOC filing or your first delivery, whichever is later. It lists who you are, who hired you, the project, and what you are furnishing. If no Notice of Commencement was filed, this requirement does not apply.
- Preliminary notice of lien rights (optional): you may file one with the superior court clerk within 30 days after you first furnish labor, services or materials; anyone other than the contractor then sends a copy to the contractor or owner within 7 days. Georgia lets you enforce a lien without it (§ 44-14-361.3(d)).
- Documentation habits: save contracts, purchase orders, delivery tickets and every notice you send or receive. Your lien and any later lien action rely on that paper trail.
What changed in Georgia lien law in 2021
If you learned Georgia lien law before 2021, the biggest change is in lien waivers. Senate Bill 315 rewrote the lien waiver statute, O.C.G.A. § 44-14-366, effective January 1, 2021.
- More time to protect yourself after signing: a statutory interim or final waiver now becomes conclusive 90 days after the date stated in it unless you file an affidavit of nonpayment before then. The old forms gave 60 days.
- Only an affidavit of nonpayment does it: the old forms let you file either an affidavit of nonpayment or a claim of lien within the 60 days. The current forms speak only of an affidavit of nonpayment.
- Advance waivers are void: a right to claim a lien cannot be waived before you furnish the labor, services or materials (§ 44-14-366(b)), and oral or written statements outside the statutory waiver forms do not waive your lien rights (§ 44-14-366(c)).
The waiver forms and the affidavit are covered in detail on our lien waivers page.
A worked example with real dates
Say a framing subcontractor's last day on a Jackson County house is Tuesday, March 3, 2026. Here is how the dates fall (an illustration only; confirm your own facts):
- Day 90 after March 3 is Monday, June 1, 2026: the last day to file the claim of lien. Filing well before then leaves room to fix a mistake.
- The sub files on Wednesday, May 20, 2026. The owner's copy must go out by Friday, May 22, 2026, two business days later.
- The lien action must be commenced within 365 days of filing: by May 20, 2027.
- If the sub files suit on March 1, 2027, the notice of commencement of lien action must be filed within 30 days, by March 31, 2027.
- If no notice of commencement of lien action is ever filed, the lien expires on its face 395 days after filing, on June 19, 2027.
- If the owner records a Notice of Contest and the sub receives it on August 3, 2026, the lien action must be commenced within 60 days of that receipt instead.
What counts as your "last day" of work
Because the 90-day clock turns on when you completed your work or furnished your materials, it matters what counts. The lien itself states the last date labor, services or materials were supplied to the premises.
Whether a late punch-list trip or warranty callback counts as completing the work is a fact question, and Georgia applies its lien deadlines strictly. Don't count on a callback to extend your deadline. The safer course is to calculate from the date your main work ended and get your specific facts reviewed before relying on a later date.
What to do if you've missed a deadline
If you missed the 90-day filing window, the owner's copy, the 365-day lien action deadline, or the 30-day notice, don't assume every option is gone. A missed lien deadline usually means you cannot rely on the lien, but other remedies may still be available: a breach of contract claim against whoever hired you, a claim against a payment bond if the project has one, and on public work, where government property generally cannot be liened, a public project payment bond claim.
The aggregate of all liens on a project cannot exceed the contract price of the improvements (§ 44-14-361.1(e)), so on a job with many unpaid trades, timing and priority matter. The sooner you get a clear read on where you stand, the more options you are likely to have.
Protect your right to payment
Georgia's lien deadlines reward contractors and suppliers who track their dates and act quickly. If you are approaching your 90-day window, unsure whether a callback affected your deadline, holding a Notice of Contest, or deciding whether it is time to move from a filed lien to a lien action, get a business law attorney involved before the calendar decides for you.
Jerry Parisi at Parisi Law Firm helps subcontractors, general contractors and material suppliers across Jefferson, Jackson County and Northeast Georgia protect their right to be paid. Business law representation is not handled on a contingency basis; the firm bills for its work rather than taking a share of your recovery. If a lien deadline is on your mind, call (404) 594-5130 or request a consultation before it passes.
Frequently Asked Questions
How long does a mechanic's lien last in Georgia?
A Georgia claim of lien stays enforceable only if you commence a lien action within 365 days of filing it and file a notice of commencement of lien action within 30 days after that. If no such notice is filed, the lien expires and is void 395 days after filing (O.C.G.A. § 44-14-367). A Notice of Contest can shorten this to 60 days.
When does the 90-day lien clock start in Georgia?
When you complete your work or furnish your materials to the project, which the lien states as the last date labor, services or materials were supplied to the premises. It is not your invoice date or contract date. Keep delivery tickets, daily logs and timesheets so you can prove that date.
Does a small warranty callback restart my lien deadline?
Don't count on it. Whether late punch-list or warranty work counts as completion of the work is a fact question, and Georgia applies lien deadlines strictly. Calculate your deadline from when your main work ended, and have your facts reviewed before relying on a later date.
Can you file a mechanic's lien in Georgia without a lawyer?
No statute requires a lawyer to record a claim of lien, but the form and mailing rules are strict and a defect can void the lien. Enforcing it is different: the lien action is a court case, and the Supreme Court of Georgia held in Eckles v. Atlanta Technology Group (1997) that only a licensed attorney may represent a corporation in a court of record.
What changed in Georgia's lien law on January 1, 2021?
Senate Bill 315 rewrote the lien waiver statute, O.C.G.A. § 44-14-366. A signed interim or final waiver now becomes conclusive after 90 days, not 60, unless you file an affidavit of nonpayment, and the forms no longer treat filing a claim of lien as an alternative to that affidavit.
What are my options if I already missed the deadline?
Missing a lien deadline usually means you can't rely on the lien itself, but other remedies may still exist, such as a breach of contract claim against whoever hired you or, on public projects, a payment bond claim. Get advice promptly, since bond claims have their own short deadlines.
Sources
- O.C.G.A. § 44-14-361.1 (filing, owner copy, lien action, notice of commencement of lien action)
- O.C.G.A. § 44-14-361 (who has a lien; amount and interest)
- O.C.G.A. § 44-14-361.3 (preliminary notice of lien rights)
- O.C.G.A. § 44-14-361.5 (Notice of Commencement and Notice to Contractor)
- O.C.G.A. § 44-14-366 (lien waivers and affidavit of nonpayment; 2020 amendment effective Jan. 1, 2021)
- O.C.G.A. § 44-14-367 (expiration of liens; 395-day statement)
- O.C.G.A. § 44-14-368 (Notice of Contest of Lien)
- Former O.C.G.A. § 44-14-366 (2019 code, 60-day waiver forms)
- Eckles v. Atlanta Technology Group, 267 Ga. 801 (1997)
Statutes and cases checked against the sources above on November 20, 2026.
Questions like this keep coming up?
The Parisi Law Firm Outside General Counsel Program puts lawyers who already know your business on a monthly subscription: contracts reviewed before you sign, questions answered, deadlines tracked. Three plans from $1,850 a month.
Related Pages
Worried About a Lien Deadline?
This article is general information, not legal advice. For help with the dates on your own job, talk to Jerry Parisi directly.