Key Takeaways
  • File the claim of lien within 90 days after you last furnished labor, services or materials, in the superior court clerk's office of the county where the property is located.
  • The lien must state that it expires and is void 395 days after filing unless a notice of commencement of lien action is filed, in at least 12-point bold type, and must tell the owner of the right to contest it.
  • Send a copy to the owner within 2 business days of filing, and to the contractor too if a Notice of Commencement was filed.
  • Sue to enforce within 365 days of filing, and file a notice of commencement of lien action within 30 days after suing. If the owner files a notice of contest, you have 60 days from receiving it.
  • Lower-tier subs and suppliers on a job with a filed Notice of Commencement must send a Notice to Contractor within 30 days or lose lien rights.

To file a mechanic's lien in Georgia, record a written claim of lien with the clerk of superior court in the county where the property is located within 90 days after your last day of work or materials, then send a copy to the owner by certified mail, registered mail or statutory overnight delivery within 2 business days. To enforce it, you must sue within 365 days of filing.

That is the core of O.C.G.A. § 44-14-361.1, and Georgia courts read it strictly. This guide walks through each step in order: checking your lien rights, the notices that may come first, what the claim of lien has to say, how and where to file (including e-filing), the owner and contractor copies, and what happens after the lien is on record, including the shortened deadline if the owner files a notice of contest. A worked timeline shows how the dates fit together.

What a mechanic's lien actually does

A mechanic's lien (Georgia's statutes also call it a materialmen's lien) is a claim recorded against real property to secure payment for labor, services or materials that improved it. Once recorded, it clouds the title: the owner generally cannot sell or refinance without dealing with it, which gives you leverage to get paid.

A lien is not a payment. It preserves your right to be paid from the property and, if necessary, sets up a lawsuit to enforce it. The total of all liens on a project cannot exceed the contract price of the improvements, and the statute is applied strictly, so shortcuts tend to backfire.

Step 1: Confirm you have lien rights on this project

Georgia's lien statute, O.C.G.A. § 44-14-361, covers most of the people and businesses that add value to a private construction project, not just the general contractor.

  • General contractors who contracted directly with the property owner.
  • Subcontractors who performed work through a general contractor.
  • Materialmen and suppliers who furnished materials used in the project.
  • Laborers who worked on the job.
  • Registered architects, engineers and land surveyors who provided services for the project.
  • Public property is the big exception. You cannot lien a school, courthouse, road or other government project; the remedy there is a claim against the public project payment bond.
  • Licensing matters too. If the job required a residential or commercial general contractor license you did not hold, no lien exists in your favor. See working without a contractor's license in Georgia.

Step 2: Check for a Notice of Commencement and send any required notices

The owner, the owner's agent or the contractor may file a Notice of Commencement with the superior court clerk within 15 days after work physically starts. Whether one was filed controls what you must do next. Georgia courts have held that a late-filed notice can still trigger the requirement for liens arising after it is filed, so check the county records more than once.

If a Notice of Commencement was filed and you did not contract directly with the general contractor, you must send a written Notice to Contractor to the owner and the contractor within 30 days after the notice was filed or after you first furnished labor or materials, whichever is later. Miss it and your lien rights are gone. General contractors and subcontractors hired directly by the general contractor do not send this notice. If you ask the contractor in writing for a copy of the Notice of Commencement and do not get one within 10 days, the Notice to Contractor requirement does not apply to you, so send that request in a way you can prove.

Separately, any lien claimant may file an optional preliminary notice of lien rights with the clerk within 30 days after delivering materials or providing labor or services (O.C.G.A. § 44-14-361.3). A lien can be enforced without one.

Step 3: Pin down your last day of work

Your 90-day clock runs from the completion of your work, or from the last day you furnished materials or machinery, not from the invoice or contract date. Keep dated records that prove when your work ended: delivery tickets, timesheets, daily logs, punch-list sign-offs.

Do not count on anything stretching the deadline. Whether later punch-list or warranty work counts as part of the original work is fact-specific, and a lien filed one day late fails. If the 90th day is close, file early rather than argue about it later.

Step 4: Prepare the claim of lien

The statute prescribes the substance of the claim, and the county clerk will check that the required language is there. A lien missing the expiration statement or the owner's notice is invalid, and clerks reject filings without the required language. At a minimum, the claim of lien should include:

  • Your name as the claimant, and the party that hired you.
  • The amount claimed: only the value of the labor, services or materials furnished and still unpaid.
  • The work, services or materials you provided.
  • A description of the real property with enough detail to identify it, and the name of the owner. A legal description from the recorded deed is the safest choice.
  • The date the claim became due.
  • On the face of the lien, in at least 12-point bold font: "This claim of lien expires and is void 395 days from the date of filing of the claim of lien if no notice of commencement of lien action is filed in that time period" (O.C.G.A. § 44-14-367).
  • A notice to the owner that the owner has the right to contest the lien (O.C.G.A. § 44-14-361.1(a)(2)).

Want a second look at your claim of lien before you file? Request a consultation.

Step 5: File within 90 days in the right county

File the claim of lien with the clerk of superior court in the county where the property is located, not where your business is or where the contract was signed. Most real estate instruments, including liens, carry a $25 clerk's filing fee under O.C.G.A. § 15-6-77; confirm the fee and any page or margin rules with the county clerk before you file.

You can file in person, by mail, or electronically. The Georgia Superior Court Clerks' Cooperative Authority (GSCCCA) accepts lien documents through its eFile Portal for participating counties, either directly (credit card payments carry a 3.5% transaction fee and bank ACH payments a $0.50 fee) or through approved submitters such as CSC, eDocs Solutions, eRecording Partners, Indecomm and Simplifile.

Step 6: Send copies within 2 business days

Within 2 business days after filing, send a true and accurate copy of the claim of lien to the property owner by registered or certified mail or statutory overnight delivery. If the owner's address cannot be found, the statute allows sending it to the contractor as the owner's agent. If the owner is an entity on file with the Secretary of State's Corporations Division, sending it to the entity's address or registered agent's address on file is enough.

If a Notice of Commencement was filed for the project, also send a copy the same way to the contractor at the address shown on that notice. Keep the mailing receipts with your copy of the recorded lien.

After filing: enforce the lien or lose it

Filing only preserves your claim. To enforce it, you must commence a lien action within 365 days from the date the claim of lien was filed, then file a notice of commencement of lien action with the clerk in the county where the lien was recorded within 30 days after you file suit. The notice is sworn and identifies the court, the case number, the filing date and the book and page of the recorded lien. If no notice of commencement of lien action is filed within 395 days, the lien expires.

If the contractor you dealt with absconds, dies, leaves the state, goes bankrupt, or your contract makes your payment depend on the contractor being paid first, the statute lets you enforce the lien directly against the property without first suing the contractor. That judgment is against the property only, and the owner can defend by proving payments were properly applied.

When you are paid, expect the owner to ask for a cancellation of the lien. The clerk cannot cancel a lien on its own; the party that filed it files the cancellation.

If the owner files a notice of contest

The owner, the contractor, or their agent or attorney may file a notice of contest of lien with the clerk and send you a copy within 7 days. It shortens your enforcement window: the statutory form says the time to commence your lien action is limited to 60 days from receiving it, and the lien is extinguished if no notice of commencement of lien action is filed within 90 days after the contest was filed (O.C.G.A. § 44-14-368). Treat a notice of contest as a signal to decide on suit right away.

A worked timeline: one lien, start to finish

Here is how the deadlines line up for a subcontractor on a private job with a filed Notice of Commencement. The dates are an example; your own dates come from your job records.

Example Georgia mechanic's lien timeline (O.C.G.A. §§ 44-14-361.1, 44-14-361.5, 44-14-367, 44-14-368)
EventExample dateDeadline rule
Notice of Commencement filed; sub first delivers materialsFeb 2 and Feb 9, 2026Notice to Contractor due within 30 days of the later date: by Mar 11, 2026
Last day of work or materialsApr 10, 2026Start the 90-day count
Claim of lien filedJun 15, 2026 (Monday)Must be within 90 days of last work: by Jul 9, 2026
Copies to owner and contractorBy Jun 17, 2026 (Wednesday)Within 2 business days of filing
Lien action filedBy Jun 15, 2027Within 365 days of filing the lien
Notice of commencement of lien action filedWithin 30 days after suitLien expires if none is filed within 395 days of filing: Jul 15, 2027
If the owner files a notice of contestAny time after filingSue within 60 days of receiving it

Georgia lien waivers and the 90-day rule

Somewhere in nearly every project, you will be asked to sign a lien waiver in exchange for payment. Georgia does not use the conditional-versus-unconditional system found in some other states. It has two statutory forms, the Waiver and Release of Lien and Payment Bond Rights Upon Interim Payment and the Waiver and Release of Lien and Payment Bond Rights Upon Final Payment, and only a waiver that substantially follows one of them can waive your lien or bond rights.

The part that catches contractors: a signed waiver becomes conclusively effective 90 days after you sign it, even if you were never paid, unless you file an affidavit of nonpayment in the property's county before the 90 days run out. Filing a lien will not stop it. Our page on Georgia lien waivers walks through both forms line by line.

Can you file a mechanics lien online in Georgia?

Yes, in participating counties. The GSCCCA eFile Portal accepts lien documents electronically, and you can file through the portal yourself or through an approved e-filing vendor. The legal requirements do not change online: the same 90-day deadline, statutory language and 2-business-day owner copy apply, and the mailed copies still go out by certified mail, registered mail or statutory overnight delivery.

Looking for a lien on a car or other repaired property?

This guide covers construction liens on real property. A repair shop's lien on a car or other personal property it repaired is a different lien under O.C.G.A. § 44-14-363. It can be kept by holding the property, must be recorded within 90 days if the property is returned to the owner (180 days for farm machinery), and is enforced through a separate foreclosure procedure.

Common mistakes that can void a lien

  • Filing even one day after the 90-day deadline from your last date of labor or materials.
  • Filing in the wrong county; it has to be the county where the property is located.
  • Leaving out the 395-day expiration statement or the notice of the owner's right to contest.
  • Failing to send the owner a copy within 2 business days of filing (and the contractor, if a Notice of Commencement was filed).
  • Skipping a required Notice to Contractor on a job with a filed Notice of Commencement.
  • Claiming more than you are owed, such as attorney fees or unrelated work.
  • Letting the 365-day enforcement window pass, missing the 30-day deadline to file notice of the suit, or ignoring a notice of contest.
  • Working without a license the job required, which leaves no lien to file.

When to call a lawyer

Mechanic's liens look simple on paper, but the deadlines are unforgiving and the paperwork has to be exact. If you are near your 90-day window, unsure whether the project is public or private, holding a lien waiver you signed before being paid, or facing a notice of contest, talk to a business law attorney before you act.

Jerry Parisi works with contractors, subcontractors and material suppliers across Jefferson, Jackson County and Northeast Georgia on mechanic's liens and payment disputes. Business law representation is not handled on a contingency fee; the firm bills for its work rather than taking a share of your recovery. Call (404) 594-5130 to talk through your options before a deadline passes.

Frequently Asked Questions

How long do I have to file a mechanic's lien in Georgia?

You must file your claim of lien within 90 days after you completed your work or last furnished materials or machinery to the project. The deadline runs from your actual last date of work, not your invoice or contract date, so keep dated job records. File early if the 90th day is close.

Who can file a mechanic's lien in Georgia?

Contractors, subcontractors, materialmen and suppliers, laborers, and registered architects, engineers and land surveyors can all claim liens if they furnished labor, services or materials that improved private property and have not been paid. Liens are not available on public property, where the remedy is a payment bond claim.

Do I need a lawyer to file a mechanics lien in Georgia?

Georgia law does not require an attorney to file a claim of lien, but the statutes are applied strictly, and an error in timing, county, required language or notice can void the lien. Enforcing it means filing a lawsuit within 365 days, so many contractors have a lawyer prepare or review the filing.

How much does it cost to file a mechanics lien in Georgia?

The clerk's fee for most real estate instruments, including liens, is $25 under O.C.G.A. § 15-6-77. E-filing directly through the GSCCCA portal adds a 3.5% fee for credit cards or $0.50 for bank ACH payments, and you will pay postage for certified or overnight copies. Confirm the fee with the county clerk.

What happens if I miss the 90-day deadline?

You generally lose the right to file a valid mechanic's lien against that property for that work. Other remedies, like a breach-of-contract claim against the party that hired you or a payment bond claim on a bonded job, may still be available, so don't assume all options are gone.

Does filing a lien guarantee I get paid?

No. Filing secures your claim against the property but does not collect the money. If the owner still doesn't pay, you must sue within 365 days of filing and file a notice of commencement of lien action within 30 days after suing, or the lien becomes unenforceable. A notice of contest shortens that to 60 days.

Questions like this keep coming up?

The Parisi Law Firm Outside General Counsel Program puts lawyers who already know your business on a monthly subscription: contracts reviewed before you sign, questions answered, deadlines tracked. Three plans from $1,850 a month.

See the plans

Need Help Filing a Lien?

This article is general information, not legal advice. For help with your own claim of lien and deadlines, talk to Jerry Parisi directly.