Construction Disputes
Construction Defect Claims in Georgia: Statute of Limitations & Repose
Reviewed by Jerry Parisi, Attorney · State Bar of Georgia No. 881415, admitted 2015 · Last reviewed . Verify with the State Bar.
- Georgia's statute of repose (O.C.G.A. § 9-3-51) bars most construction defect lawsuits filed more than eight years after substantial completion. If the injury happens in year seven or eight, a tort suit can still be filed within two years of it, but never more than ten years after completion.
- Negligent construction claims for property damage have a four-year statute of limitations (O.C.G.A. § 9-3-30) that usually runs from substantial completion, not from the day you discover the defect.
- Claims on a written contract or express warranty have six years (O.C.G.A. § 9-3-24), and since a 2020 amendment the statute of repose does not apply to breach of contract claims.
- For homes, Georgia's Right to Repair Act requires written notice to the contractor at least 90 days before filing suit and gives the contractor a chance to inspect and offer a fix.
- The substantial completion date anchors most of these deadlines, so pin it down first.
A leaky roof, a cracked foundation, a slab that keeps settling: construction defects often show up long after the crew has moved on to the next job. When they do, the property owner and the contractor ask the same question. Is it too late to do anything about it?
Georgia answers with several clocks that run at the same time. There is a statute of limitations that depends on the kind of claim, an eight-year statute of repose that caps most claims no matter when the defect is found, and, for homes, a notice process that has to happen before anyone files suit. This guide walks through each one with the statute behind it, a worked example, and what owners and contractors should do now.
What Counts as a Construction Defect Claim
A construction defect claim alleges that work on a building or other improvement was done improperly, through faulty design, substandard materials, poor workmanship, or a failure to follow code, and that the result is damage or a condition that falls short of what the contract and applicable standards required.
Defects generally fall into three groups: design defects (the plans were flawed), material defects (products failed or were the wrong ones), and workmanship defects (sound plans and materials were installed badly). Some are obvious right away, like a door that won't close or water pooling on a new driveway. Others, like slow foundation settlement or water getting behind a wall, can take years to surface.
In Georgia these claims are brought by owners against general contractors, by general contractors against subcontractors, and sometimes by later buyers. Whoever brings the claim, timing is usually the first thing that gets litigated, because the answer depends on what kind of claim it is.
Statute of Limitations vs. Statute of Repose: What's the Difference?
A statute of limitations sets a deadline for filing suit that runs from when the claim accrues. What "accrues" means depends on the claim, and in Georgia construction cases it is often earlier than people expect (see the next sections).
A statute of repose runs from a fixed event, which for construction is substantial completion of the improvement, regardless of when or whether anyone discovers a problem. Once the repose period ends, the claim is gone, even if the defect was hidden the whole time. Georgia's courts treat § 9-3-51 as a statute of ultimate repose that does not lengthen the four-year limitation period in § 9-3-30 (Armstrong v. Royal Lakes Associates).
The Supreme Court of Georgia has also explained why repose is so final: it creates a substantive, vested right to be free from liability once the period runs, not just a procedural deadline (Southern States Chemical v. Tampa Tank & Welding, decided May 31, 2023).
What Is the Statute of Repose for Construction in Georgia?
Eight years from substantial completion. Under O.C.G.A. § 9-3-51(a), no action to recover damages for a deficiency in the survey or plat, planning, design, specifications, supervision or observation of construction, or construction of an improvement to real property, or for injury to property, personal injury or wrongful death arising out of that deficiency, can be brought against the person who performed or furnished that work more than eight years after substantial completion.
There is one extension. If the injury to property or to a person happens during the seventh or eighth year after substantial completion, an action in tort can be brought within two years after the injury, but in no event more than ten years after substantial completion (§ 9-3-51(b)).
Breach of contract claims are now outside the repose statute. In 2019 the Court of Appeals had applied the eight-year bar to contract claims. The General Assembly responded with Senate Bill 451, which added § 9-3-51(c): the statute "shall not apply to actions for breach of contract, including, but not limited to, actions for breach of express contractual warranties." The act took effect July 1, 2020.
The amendment does not reach back to claims that were already extinguished. In Southern States Chemical (2023), a tank renovation was substantially completed in January 2002, so the eight years had long run before 2020. The Supreme Court of Georgia held that the defendant had a vested right to repose and that the 2020 amendment cannot be applied retroactively to revive the owner's breach of warranty claim.
Georgia Statute of Limitations for Construction Defects, by Claim Type
Inside the repose window, each type of claim has its own limitation period. The same defect can support more than one claim, and they can expire on different dates.
| Claim | Deadline | When the clock usually starts | Statute |
|---|---|---|---|
| Negligent construction causing damage to real property | 4 years | Substantial completion; Georgia does not apply a discovery rule to property-damage-only claims | O.C.G.A. § 9-3-30(a) |
| Breach of a written contract or express warranty | 6 years | When the contract is breached, which in construction is often completion of the work | O.C.G.A. § 9-3-24 |
| Breach of an oral contract or implied promise | 4 years | When the claim accrues | O.C.G.A. § 9-3-25 |
| Personal injury caused by a defect | 2 years | The date of the injury | O.C.G.A. § 9-3-33 |
| Damage to a home from defective synthetic exterior siding | 4 years | When the damage is discovered or should have been discovered | O.C.G.A. § 9-3-30(b) |
| Statute of repose (tort claims for a design or construction deficiency) | 8 years, or up to 10 if the injury occurs in year 7 or 8 | Substantial completion, regardless of discovery | O.C.G.A. § 9-3-51 |
Courts look at what a claim really is, not the label on it. In Costrini v. Hansen Architects (2000), the six-year contract period applied to a claim for breach of a contract to build an office building. In Wilks v. Overall Construction (2009), a homeowner who sued in 2007 over interior work substantially completed in 1999 was out of time even under the six-year contract period. For contract claims more generally, see how long you have to sue over a business contract in Georgia.
Not sure which deadline applies to your project? Request a consultation with Jerry Parisi.
Hidden (Latent) Defects: Does the Clock Wait Until You Find Them?
Usually not. For claims that seek only property damage, Georgia does not use a discovery rule. The Supreme Court of Georgia held in Corporation of Mercer University v. National Gypsum (1988) that an action under § 9-3-30 must be brought within four years of substantial completion, and later Court of Appeals decisions say the same, including Stamschror v. Allstate (2004), where a claim over wiring installed in a house was barred four years after the house was finished.
There are narrow exceptions. Damage to a home from defectively made or installed synthetic exterior siding accrues when the damage is discovered or should have been (§ 9-3-30(b)), but those claims still have to meet the repose deadline. The discovery rule Georgia does recognize is confined to bodily injuries that develop over time.
Two other rules catch people out. Later repairs do not restart the clock, because the right of action accrued at substantial completion (Heffernan v. Johnson, 1993). And a later buyer cannot revive a claim that was already barred for the original owner (U-Haul Co. v. Abreu & Robeson, 1981), although a buyer's own claim against the builder who sold the home may run from the purchase (Colormatch Exteriors v. Hickey, 2002).
When Is a Project Substantially Complete?
Because the four-year limitation period and the eight-year repose period both start here, this date often decides the case. For a house, the certificate of occupancy is usually the first document anyone looks at. On one commercial project, the four-year period ran from the last work performed because that work was what made the building substantially complete (Broadfoot v. Citizens & Southern National Bank, 1993).
Contracts often define substantial completion and require a certificate or sign-off. Keep the certificate of occupancy, the architect's certificate of substantial completion if there is one, punch-list records, and the dates of final inspections. If a project was finished in phases, each phase may have its own date.
A Worked Example: One House, Five Dates
Say a new house receives its certificate of occupancy on March 1, 2019, and that is its substantial completion date. Here is how the clocks run (a simplified illustration, not a prediction for any real case):
- March 1, 2023 (four years): a negligent construction claim for water damage to the house is generally barred after this date, even if the leak was not found until 2024.
- March 1, 2025 (six years): a claim that the builder breached the written construction contract generally has to be filed by now if the breach happened at completion. Because the eight years had not run by July 1, 2020, the 2020 amendment keeps this contract claim outside the repose statute.
- March 1, 2027 (eight years): the statute of repose bars tort claims against the builder and designers for the construction or design deficiency, no matter who discovers it or when.
- June 1, 2026: a deck collapses and injures a guest. That is in year eight, so the guest can sue in tort within two years of the injury, until June 1, 2028, which is still inside the ten-year cap of March 1, 2029.
- Any time before suing: if the owner wants to sue the builder over the house, the Right to Repair Act notice has to be served at least 90 days before filing.
Georgia's Right to Repair Act: Notice Before You Sue Over a Home
For claims about a dwelling or a common area of a condominium or other common interest community, Georgia requires a pre-suit process (O.C.G.A. §§ 8-2-35 to 8-2-43). The legislature's stated goal is to give the contractor an opportunity to resolve the claim without litigation. The steps and deadlines come straight from § 8-2-38:
- Step 1, notice of claim: at least 90 days before filing suit or arbitration, the owner serves the contractor with a written notice that describes the defects and their results in detail and includes evidence such as expert reports, photos and videos. Service means certified mail, return receipt requested, or statutory overnight delivery (§ 8-2-36).
- Step 2, the contractor's response: within 30 days the contractor must either offer to settle (money, repairs, or both) without inspecting, or propose an inspection.
- Step 3, inspection: the owner must give reasonable access within 30 days of the proposal, including for testing. If destructive testing is needed, the contractor gives advance notice and restores the home afterward.
- Step 4, the offer: within 14 days after the inspection, the contractor serves an offer to repair, to pay, a combination, or a written statement that it will not proceed, with reasons.
- Step 5, accept or reject: the owner accepts in writing within 30 days. If the owner does not respond within 30 days, the offer is deemed accepted. A rejection must be in writing with the reasons, and the contractor then has 15 days to make a supplemental offer.
The consequences are real. An owner who rejects a reasonable offer cannot recover more than the value of that offer, and cannot recover costs or attorney's fees incurred after the rejection (§ 8-2-38(l)). A lawsuit filed without following the process is stayed until the owner complies, although a claim for personal injury or death is not stayed (§ 8-2-37). If a limitation period is about to run during the process, the owner may file suit and the case is stayed, but the process does not revive an expired limitation period or extend the statute of repose (§ 8-2-38(o)).
Contractors have obligations too. A contract for the sale, construction or improvement of a dwelling must include a conspicuous notice of the right to repair (§ 8-2-41). If the statute and the contract conflict, the contract controls (§ 8-2-43(c)). And the Act does not apply to a contractor who was not required to be licensed under Georgia's contractor licensing law (§ 8-2-43(d)), one more reason to understand Georgia contractor license requirements.
Defending a Construction Defect Claim as a Contractor
If you are a contractor facing a defect allegation, timing is often the first line of defense, but it is rarely the only one.
- Pin down the substantial completion date and measure it against the four-year, six-year and eight-year deadlines above.
- Sort the claims: negligence, written contract, implied contract and personal injury claims each run on their own clock, and only some are subject to repose.
- On a home, check whether the owner served a Right to Repair notice and calendar your 30-day response deadline the day it arrives.
- Pull the contract, plans, specifications and change orders to see what was promised, and any warranty terms, which now matter more because contract and warranty claims are outside the repose statute.
- Identify who did the work. A subcontractor's scope and warranty may shift responsibility, and the Right to Repair Act does not govern your own claims for contribution or indemnity against subs, suppliers or design professionals (§ 8-2-43(b)).
- Notify your insurance carrier early. Many defect claims implicate commercial general liability coverage.
Many construction contracts also require mediation or arbitration before suit. See construction mediation and arbitration for how those clauses work alongside these deadlines.
Contractor Protections: Contracts, Warranties, and Documentation
The best defense to a defect claim is usually built long before the claim shows up.
- Use written construction contracts that spell out scope, materials, standards, change-order procedures and how substantial completion is certified.
- On residential work, put the Right to Repair notice in the contract in conspicuous form, as § 8-2-41 requires.
- Write warranties with a defined length, scope and exclusions, so everyone knows what is covered and for how long. The flooring warranty guide shows how this plays out in one trade.
- Keep project records: plans, specs, inspection reports, photos, correspondence and material invoices, for well beyond the eight-year repose period, since contract claims can now run on their own schedule.
- Record the substantial completion date formally with a certificate of occupancy or a signed completion certificate.
- Respond to warranty and punch-list issues promptly and in writing. A documented pattern of responsiveness helps if a bigger claim arrives later.
If You're an Owner: Don't Wait to Act
If you suspect a defect, the deadlines above cut both ways. The four-year clock for property damage may already be running, or nearly finished, before you see the first crack. Photograph the problem, gather the contract, warranty and completion paperwork, and get the timeline evaluated before you assume you have time.
On a home, budget for the Right to Repair process: 90 days of notice before filing, plus the inspection and offer steps. Starting late can leave you filing a protective suit just to stop a limitation period from running.
Parisi Law Firm represents general contractors, subcontractors and property owners across Jefferson, Jackson County and Northeast Georgia in construction disputes and business litigation. Business law matters are not handled on a contingency basis. If a defect claim is coming your way, or you need to send or answer a Right to Repair notice, request a consultation.
Frequently Asked Questions
How long can a contractor be sued for a defect in Georgia?
For most tort claims, no more than eight years after substantial completion under the statute of repose (O.C.G.A. § 9-3-51), or up to ten years if the injury happens in year seven or eight. Shorter limitation periods often end the claim sooner, such as four years from completion for property damage. Contract claims are outside the repose statute but have a six-year limit.
How long do you have to sue a contractor for bad work in Georgia?
It depends on the claim. Negligent construction causing property damage: four years, usually from substantial completion (§ 9-3-30). Breach of a written contract or express warranty: six years from the breach (§ 9-3-24). Oral contracts: four years (§ 9-3-25). Personal injury: two years from the injury (§ 9-3-33). Tort claims are also capped by the eight-year repose period.
What's the difference between a statute of limitations and a statute of repose?
A statute of limitations runs from when a claim accrues. A statute of repose runs from a fixed event, substantial completion, regardless of discovery. The Supreme Court of Georgia has held that repose creates a vested right to be free from liability once the period ends, so it cannot be extended or revived the way a limitation period sometimes can.
Does Georgia's statute of repose apply to breach of contract or warranty claims?
Not anymore. A 2020 amendment, O.C.G.A. § 9-3-51(c), says the statute does not apply to breach of contract actions, including breach of express contractual warranties. But it cannot revive claims where the eight years had already run before the amendment took effect, as the Supreme Court of Georgia held in 2023.
Can you sue a builder 20 years later in Georgia?
Almost never for the construction defect itself. Tort claims are barred eight years after substantial completion, or ten at most, and contract claims carry a six-year limit that usually starts at completion. A claim that far out would have to rest on something other than the original design or construction, which is rare.
Do I have to notify the builder before suing over a defect in my home?
Yes, for most claims covered by Georgia's Right to Repair Act. Serve a detailed written notice of claim at least 90 days before filing, by certified mail or statutory overnight delivery. The contractor then has 30 days to offer a fix or payment or to propose an inspection. Personal injury claims are not stayed by the process.
Sources
- O.C.G.A. § 9-3-51 (statute of repose, including subsection (c))
- O.C.G.A. § 9-3-30 (damage to realty) and the judicial decisions noted under it
- O.C.G.A. § 9-3-24 (written contracts)
- O.C.G.A. § 9-3-25 (oral contracts and implied promises)
- O.C.G.A. § 9-3-33 (injuries to the person)
- O.C.G.A. § 8-2-38 (Right to Repair Act procedure; see §§ 8-2-35 to 8-2-43)
- O.C.G.A. § 8-2-41 (required notice in residential contracts)
- Senate Bill 451 (2020), amending § 9-3-51
- Southern States Chemical v. Tampa Tank & Welding (Supreme Court of Georgia, May 31, 2023)
Statutes and cases checked against the sources above on November 20, 2026.
Questions like this keep coming up?
The Parisi Law Firm Outside General Counsel Program puts lawyers who already know your business on a monthly subscription: contracts reviewed before you sign, questions answered, deadlines tracked. Three plans from $1,850 a month.
Related Pages
Facing a Construction Defect Deadline?
This article is general information, not legal advice. For advice on the dates in your own project, talk to Jerry Parisi directly.

