Parisi Law Firm — Personal Injury & Business Lawyer in Jefferson, GA

Mechanic's Liens

Can a Subcontractor File a Lien in Georgia?

June 21, 2026 7 min readBy Parisi Law Firm
Key Takeaways
  • Yes — subcontractors can file mechanic's liens in Georgia, along with sub-subcontractors, materialmen, and laborers.
  • You don't need a direct contract with the property owner to have lien rights.
  • Subs must watch preliminary-notice requirements and the strict 90-day filing / 365-day enforcement deadlines.
  • A pay-if-paid clause in your contract doesn't erase your right to file a lien against the property.
  • You can't lien public or government property — on those jobs, a payment bond claim is your remedy instead.

You did the work, the general contractor got paid by the owner, and somehow the money never made it to you. If you're a subcontractor in Georgia, the good news is you're not stuck simply hoping the GC eventually pays up. Georgia's mechanic's lien law was written with subcontractors, sub-subcontractors, materialmen, and laborers in mind — not just the contractor who signed the contract with the owner.

This post answers the core question — can a subcontractor file a lien in Georgia — and walks through who qualifies, the notice steps that protect your claim, the deadlines you can't miss, and a contract clause that trips up a lot of subs: the pay-if-paid provision. If you're not being paid for work you completed, this is where to start.

Short answer: yes, subcontractors can file

Georgia's lien statute is not limited to general contractors. Subcontractors, sub-subcontractors, materialmen, suppliers, laborers, and design professionals can all claim a lien against the improved property if they furnished labor, materials, or services and haven't been paid. The law recognizes that a project's value comes from everyone who touched it, not just the party holding the prime contract.

That said, being eligible to file a lien and actually having an enforceable lien are two different things. Subcontractors face a few wrinkles that general contractors dealing directly with the owner don't — particularly around notice — so it's worth understanding exactly where you stand before you assume your lien rights are automatically preserved.

Who qualifies to file

Georgia's lien framework covers most of the people and businesses that add value to a construction project, regardless of who they contracted with directly.

  • Subcontractors who contracted with the general contractor, not the property owner.
  • Sub-subcontractors who contracted with a subcontractor further up the chain.
  • Materialmen and suppliers who furnished materials incorporated into the project.
  • Laborers who performed work on the job.
  • Design professionals, such as architects and engineers, who provided services for the project.

You don't need a contract with the owner

This is the point that surprises a lot of subs: you don't need any direct contractual relationship with the property owner to file a valid lien. Your contract is with the general contractor, but your lien attaches to the owner's property. That's the entire purpose of lien law — it gives the people who did the work a way to reach the asset they improved, even though their paperwork runs through someone else.

That doesn't mean the process is identical to a GC's. Because you're a step (or two) removed from the owner, Georgia's notice framework exists to make sure the owner knows who's working on their property and who might have a claim against it.

The notice steps subs have to follow

Georgia uses a Notice of Commencement / Notice to Contractor / preliminary-notice framework to keep owners, GCs, and subs informed of who is on a job. Depending on your position in the contracting chain, you may need to send — or watch for — these notices before you ever get to the lien-filing stage.

The owner or GC may file a Notice of Commencement at the start of a project. In response, subcontractors and suppliers may need to send a Notice to Contractor to preserve their position. Skipping this step doesn't necessarily kill your underlying right to be paid, but it can complicate or jeopardize your ability to rely on a lien later. Treat preliminary notices as part of your paperwork routine on every job, not an afterthought you deal with only after a payment dispute starts.

The 90-day and 365-day deadlines

Once you decide to file, the clock is unforgiving and doesn't bend for subcontractors any more than it does for general contractors.

  • 90 days to file: Your claim of lien must be filed within 90 days of the last day you furnished labor or materials to the project. That's your actual last date of work — not your invoice date or the date the GC promised to pay.
  • File in the right county: The lien must be filed in the superior court clerk's office of the county where the property is located.
  • 2 business days to notify the owner: After filing, you must send the property owner a copy of the recorded lien within 2 business days.
  • 365 days to enforce: Filing the lien only preserves your claim — it doesn't collect money. You must file a lawsuit to enforce the lien within 365 days of the date it was filed, or the lien generally becomes unenforceable.

How pay-if-paid clauses interact with your lien rights

Many subcontracts include a pay-if-paid clause, which conditions the GC's obligation to pay the sub on the GC first getting paid by the owner. GCs use these clauses to shift the risk of an owner's nonpayment down the contracting chain, and if you've had a job stall out because the owner stopped paying the GC, you've likely run into one.

A pay-if-paid clause is a provision in your contract with the general contractor — it governs when the GC owes you money under that contract. It does not, by itself, erase your separate statutory right to file a lien against the property for unpaid labor or materials. Your lien rights come from Georgia's mechanic's lien statute, not from the payment terms the GC wrote into your subcontract. If you're facing a pay-if-paid dispute, don't assume it automatically forecloses your lien options — that's exactly the kind of situation worth reviewing with a business law attorney before your 90-day window closes.

Public projects: no lien, but a bond claim instead

One major exception applies to everyone in the contracting chain, subs included: you cannot file a mechanic's lien against public or government-owned property in Georgia. If you're working on a school, courthouse, road, or other government job, lien law simply doesn't reach that property.

Your remedy on a public project is a claim against the project's payment bond instead. Public jobs typically require the prime contractor to post a payment bond precisely so subcontractors and suppliers have a way to get paid when a lien isn't available. If you're not sure whether your project counts as public work, confirm that before you assume lien rights apply — the deadlines and procedures for a bond claim are not the same as for a lien.

How subs protect themselves

A few habits go a long way toward keeping your lien and bond rights intact on every job, whether or not a payment dispute ever materializes.

  • Keep dated records of your last day of labor or materials on every job — delivery tickets, timesheets, and punch-list sign-offs matter.
  • Track and respond to Notices of Commencement and send Notices to Contractor when your role requires it.
  • Read every lien waiver before you sign it, and understand whether it's conditional or unconditional.
  • Confirm early whether a project is public or private, since that determines whether you'll be relying on a lien or a bond claim.
  • Don't let a pay-if-paid clause talk you out of preserving your lien rights within the 90-day window.

When to call a lawyer

Subcontractor lien rights exist, but the notice requirements and strict deadlines mean it's easy to lose them through inaction rather than any fault of your own. If you're approaching your 90-day window, unsure whether you sent the right preliminary notice, wrestling with a pay-if-paid clause, or trying to figure out whether your project is public or private, it's worth talking to a business law attorney before the clock runs out.

Jerry Parisi at Parisi Law Firm works with subcontractors, materialmen, and laborers across Jefferson, Jackson County, and Northeast Georgia to protect their right to get paid for completed work. Business law representation like this is not handled on a contingency basis — the firm bills for its work rather than taking a share of your recovery, so you know what to expect going in. If a GC or owner isn't paying you for work you've done, contact Parisi Law Firm at (404) 594-5130 to talk through your options before a deadline passes.

Frequently Asked Questions

Can a subcontractor file a lien in Georgia?

Yes. Georgia's mechanic's lien law covers subcontractors, sub-subcontractors, materialmen, suppliers, and laborers, not just general contractors. If you furnished labor or materials to a project and haven't been paid, you may be able to file a claim of lien against the property.

Do I need a contract with the owner to file a lien?

No. Your subcontract runs through the general contractor, but your lien attaches to the property itself. Georgia law gives subcontractors lien rights precisely because they add value to the project even without a direct agreement with the property owner.

What notices does a subcontractor have to send?

Georgia uses a Notice of Commencement / Notice to Contractor / preliminary-notice framework. Depending on your position in the contracting chain, you may need to send a Notice to Contractor in response to the owner's or GC's Notice of Commencement to help preserve your position before filing a lien.

Does a pay-if-paid clause kill my lien rights?

No. A pay-if-paid clause governs when the general contractor owes you money under your subcontract, but it doesn't erase your separate statutory right to file a lien against the property for unpaid labor or materials. The two are governed by different sources of law.

Can I lien a public or government project?

No. Georgia law does not allow liens against public or government-owned property. On public jobs, your payment remedy is a claim against the project's payment bond instead, which follows its own procedures and deadlines.

Have a Question About Your Business?

This article is general information, not legal advice. For guidance on your specific situation, talk to Jerry Parisi directly.

Free. Confidential. No Obligation.

Ready to Talk?
We're Here to Help.

Get a 100% free case review from Jerry Parisi. You don't pay a single dollar unless we win your case.